Recommencement of Hauling Operations

The 311 Mapleton development has been progressing on-site for the last four weeks, which has allowed for minimizing the truck traffic through the neighborhood. We are continuing to stockpile as much dirt as possible on-site, but after the recent pause, hauling must recommence. 


Next week, hauling operations will resume and run to completion, which is expected to take about three weeks. Saunders will continue to monitor trucks to the best of their capability, ensuring that they use designated routes, adhere to noise ordinances, and remain respectful to other drivers and pedestrians. 