Recommencement of Hauling Operations

Updated: Sep 23

The 311 Mapleton development has been progressing on-site for the last four weeks, which has allowed for minimizing the truck traffic through the neighborhood. We are continuing to stockpile as much dirt as possible on-site, but after the recent month-long pause, hauling must recommence. 


Next week, hauling operations will resume and run to completion, which is expected to take about three weeks. Saunders will continue to monitor trucks to the best of their capability, ensuring that they use designated routes, adhere to noise ordinances, and remain respectful to other drivers and pedestrians. 

Recent Posts

See All

10/23/20 Hauling + Development Update

The estimated completion date for current hauling and excavation is now the first week of November. This extension is due to eight days of no hauling from 9/28 - 10/7, continued difficulties with dens

Paving Operation Rescheduled for Monday 9/21

The paving operation initially scheduled for tomorrow, Saturday 9/19, will now occur on Monday, 9/21. The road prep crew has not made enough progress and needs another day for compaction and grading b