Development Update - October 2023

October Milestones

Scopes starting or continuing in the month of October:

  • Landscaping – All Month

  • Site Concrete (Sidewalks) – Only at West side behind buildings

  • Site Retaining Walls – All Month – West side of project only

  • Site Fountain filling / start up

  • Pool equipment start up and testing

  • Exterior Flatwork - Villa's

  • Flooring - J3-4/J5-J6 Villa's

  • Interior Trim - Villa's

  • Landscaping/Irrigation - Villa's

  • Siding - J1/J2 Villa's

  • Masonry - Villa's

  • Garage Door Install - Villa's

  • Framing for R5

  • Pour garage floors - R5/R7 Cottages

  • Dry-in - R5 Cottage

  • Electrical rough-in - R7 Cottage

  • Fire suppression system - R7 Cottage

  • Elevator install - R7 Cottage

  • Front Porch slab pour - R6/R7 Cottages

  • Truss install - R5 Cottage

  • Window install - R5 Cottage

  • Rough plumbing - R5 Cottage

  • Siding install - R7 Cottage

  • Start rough plumbing - R6 Cottage


Construction progress aerial footage | September 2023


Trucking Impacts

Rosch Retaining Wall Material – Approximately 2 trucks per week*

Irrigation/Landscaping Material – Approximately 4 trucks per week*

Drywall delivery – Villa's - approximately 4 trucks*

Flooring delivery – Villa's - approximately 2 trucks*

Concrete Pour Dates

  • Basement pour - R5 Cottage - 10/20/23

  • Front porch pour - R7/R6 Cottages - 10/21/23


Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.


Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:


Construction progress aerial footage | September 2023


General Construction Activity


  • Pool house finishes (Equipment Start Up & Testing)

  • Landscaping

  • Final Painting – Punchlist work

  • Elevator final acceptance by State of Colorado & City of Boulder

  • Excavation – final grading – West side of project only

  • Roofing - Villa's

  • Rough MEPs - Villa's

  • Siding - Villa's

  • Insulation - Villa's

  • Drywall - Villa's

  • Elevator Install - Villa's

  • Exterior Flatwork - Villa's

  • Flooring/Tile - Villa's

  • Garage Concrete - Villa's