October Milestones
Scopes starting or continuing in the month of October:
Landscaping – All Month
Site Concrete (Sidewalks) – Only at West side behind buildings
Site Retaining Walls – All Month – West side of project only
Site Fountain filling / start up
Pool equipment start up and testing
Exterior Flatwork - Villa's
Flooring - J3-4/J5-J6 Villa's
Interior Trim - Villa's
Landscaping/Irrigation - Villa's
Siding - J1/J2 Villa's
Masonry - Villa's
Garage Door Install - Villa's
Framing for R5
Pour garage floors - R5/R7 Cottages
Dry-in - R5 Cottage
Electrical rough-in - R7 Cottage
Fire suppression system - R7 Cottage
Elevator install - R7 Cottage
Front Porch slab pour - R6/R7 Cottages
Truss install - R5 Cottage
Window install - R5 Cottage
Rough plumbing - R5 Cottage
Siding install - R7 Cottage
Start rough plumbing - R6 Cottage
Construction progress aerial footage | September 2023
Trucking Impacts
Rosch Retaining Wall Material – Approximately 2 trucks per week*
Irrigation/Landscaping Material – Approximately 4 trucks per week*
Drywall delivery – Villa's - approximately 4 trucks*
Flooring delivery – Villa's - approximately 2 trucks*
Concrete Pour Dates
Basement pour - R5 Cottage - 10/20/23
Front porch pour - R7/R6 Cottages - 10/21/23
Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.
Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:
Construction progress aerial footage | September 2023
General Construction Activity
Pool house finishes (Equipment Start Up & Testing)
Landscaping
Final Painting – Punchlist work
Elevator final acceptance by State of Colorado & City of Boulder
Excavation – final grading – West side of project only
Roofing - Villa's
Rough MEPs - Villa's
Siding - Villa's
Insulation - Villa's
Drywall - Villa's
Elevator Install - Villa's
Exterior Flatwork - Villa's
Flooring/Tile - Villa's
Garage Concrete - Villa's