top of page
Writer's picture311 Mapleton Development

Development Update - August 2023

August Milestones

New scopes will be starting or continuing in August:

  • Site Pavers

  • Landscaping – All Month

  • Site Concrete (Sidewalks)

  • Site Retaining Walls – All Month

  • Site Fountains

  • Asphalt – Paving of roadways has been pushed to the end of August or Early September

  • Windows/Siding - J1-J2 Villas

  • Elevator Install - J3-J4/J5-J6 Villas

  • Rough MEPs - J1-J2 Villas

  • Fire Alarm Wiring

  • Exterior Flatwork

  • Flooring - J3-4/J5-J6 Villas

  • Xcel Gas Laterals

  • Pour footings and walls - R5 Cottage

  • UG pluming - R5 Cottage

  • Concrete window well set - R5 Cottage

  • Backfill - R5 Cottage

  • Basement slab pour - R5 Cottage

  • Garage slab pour - R5 Cottage

  • Front Porch slab pour - R6/R7 Cottages

  • Truss install - R6/R7 Cottages

  • Dry-in - R6/R7 Cottages

  • Start rough HVAC - R7 Cottage

  • Start rough plumbing - R7 Cottage

  • Start siding - R6/R7 Cottages


Construction progress aerial footage | July 2023


Trucking Impacts

  • Paver Material – Approximately 1 truck per week through the middle of August*

  • Rosch Retaining Wall Material – Approximately 2 trucks per week*

  • Pool Tile & Finishes – Approximately 1 truck per week*

  • Interior Doors & Trim – Approximately 1 trucks per week*

  • Balcony Railings – Approximately 1 truck per week*

  • Irrigation/Landscaping Material – Approximately 3 trucks per week*

  • Drywall delivery | Villas - Approximately 2 trucks per week*

  • Flooring delivery | Villas - Approximately 2 trucks*

  • Import | R5-R7 Cottages - Approximately 3 trucks 8/17/23*

  • Concrete Pour Dates:

    • Villas - 8/15 - 8/17

    • R5-R7 Cottages

      • Footing pour | R5 Cottage - 8/12/23

      • Foundation walls | R5 Cottage - 8/20/23

Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.


Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:


4th Street Work / Public Access


Mapleton Work

  • Street traffic control impact on Mapleton – Complete on Wednesday 8/9/23

  • The sidewalk will be opened for public use by approximately 8/11/23


Construction progress aerial footage | July 2023


Comments


bottom of page