Monthly Development Update - July 2021

311 Mapleton Monthly Development Update | July 2021


Milestones

  • July will see the first large scale concrete slab pours of the project.


General Construction Activity

  • Underground Building Utilities

  • Concrete Foundations

  • Foundation Waterproofing

  • Backfill of Foundations


Trucking Impacts

  • Reinforcing Steel for Concrete – Approximately 1 truck per day*

  • Underground Utilities – Approximately 1 truck*

  • Concrete Pour Dates – Approximately 2-10 trucks per date *unless noted otherwise

Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather or other events that may cause delays. If dates change, the original will have a strikethrough. The new date will be shown after the original and updated on the monthly update article and construction calendar.

*Semi-truck-sized vehicles and heavy impact deliveries associated with the 311 Mapleton development are required to use Dellwood and Alpine routes through the project's duration. All smaller trucks will use the best available public roads.