September Milestones

New scopes will be starting in the month of September:

  • Elevators B/FG – 9/1

  • Parapet Caps / Gutters / Downspouts – 9/1

  • Standing Seam Metal Roof – 9/2

  • Parking Striping – 9/26

  • Perforated Metal Panels – 9/15

Construction progress aerial footage | August 2022


Trucking Impacts

  • Parapet Caps / Gutters / Downspouts – Approximately 2 trucks per week*

  • Roofing Material – Approximately 1 truck per week*

  • Shower Doors – Approximately 1 truck per week*

  • Storefront / Glass Partitions – Approximately 1 truck per week*

  • Unit Appliances – Approximately 1 truck per week*

  • Patio Pavers – Approximately 1 truck per week*

  • Balcony Railings – Approximately 2 truck per week*

  • Flooring Material – Approximately 3 trucks per week*

  • Cabinets / Millwork – Approximately 2 truck per week*

  • Interior Doors & Trim – Approximately 3 trucks per week*

  • Insulation & Drywall – Approximately 3 trucks per week*

  • Brick Veneer – Approximately 2 trucks per week*

  • Steel – Approximately 1 trucks per week*

  • MEPF Material – Approximately 6 trucks per week*

  • Irrigation/Landscaping Material – Approximately 2 trucks per week*

  • Underground Utility Material – Approximately 2 trucks per week*

  • Concrete Pour Dates

    • Building – K (Pool)

- Form and Pour Pool Deck – 9/15 ~15-20 trucks*

  • Building – E (Reception)

- Foundation Walls – Pour 1 – 9/7 ~10 trucks*

- Foundation Walls – Pour 2 – 9/22 ~10 trucks*

- Slab on Metal Deck – 10/13 ~15-20 trucks*


Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.


Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:


Construction progress aerial footage | August 2022

bottom of page