June Milestones
New scopes will be starting in the month of June:
Exterior Metal Panels – All Month
Garage Doors – All Month
Site Pavers – All Month
Landscaping – All Month
Site Concrete (Sidewalks) – All Month
Site Curb and Gutter Replacement – All Month
Site Retaining Walls – All Month
Site Fountains – All Month
Asphalt – Last two weeks of June
Insulation - J3-J6 Villas
Drywall - J3-J6 Villas
Rough MEPs - H1-H2 / J1-J2 Villas
Windows/Siding - H1-H2 / J1-J2 Villas
Fire Alarm - J3-J6 Villas
Stake new foundation - R5 Cottage
UG plumbing - R6/R7 Cottages
Concrete window well set - R6/R7 Cottages
Backfill - R6/R7 Cottages
Basement slab pour - R6 and R7 Cottages
Garage slab pour - R6/R7 Cottages
Front Porch slab pour - R6/R7 Cottages
Footing pour - R5 Cottage
Foundation Pour - R5 Cottage
Start of framing - R7 Cottage
Start of framing - R6 Cottage
Construction progress aerial footage | May 2023
Trucking Impacts
Site Paver Material – Approximately 1 truck per week*
Rosch Retaining Wall Material – Approximately 2 trucks per week*
Pool Tile & Finishes – Approximately 1 truck per week*
Flooring Material – Approximately 2 trucks per week*
Interior Doors & Trim – Approximately 3 trucks per week*
Countertop Material – Approximately 3 truck per week*
Roofing Material – Approximately 1 truck per week*
Storefront / Glass Partitions – Approximately 2 truck per week*
Unit Appliances – Approximately 1 trucks per week*
Balcony Railings – Approximately 1 trucks per week*
Irrigation/Landscaping Material – Approximately 3 trucks per week*
Lumber delivery | Villas – approximately 1 truck per week
Drywall delivery | Villas - approximately 2 trucks per week
Insulation | Villas - approximately 2 trucks per week
Dirt import | R5/R6/R7 Cottages - June 15-17th
Concrete Pour Dates
Building – E (Reception)
- Concrete Sidewalks & Stairs – approximately 2 trucks
- Fountain Foundations – approximately 2 trucks
Building A (Site Work)
- Concrete Sidewalks & Stairs – approximately 3 trucks
- Slab on Grade for Pavers at Courtyard – approximately 2 trucks
- Concrete Sidewalks & Stairs at A-North – approximately 2 trucks
Building B (Site Work)
- Pour Bridge Deck and Stairs – approximately 2 trucks
J1/J2 Villas
- Foundation Walls - 4/7 - approximately 12 trucks*
R6/R7 Cottages
-Basement slabs | R6/R7 Cottages - 6/15 - approximately 3 trucks*
-Footing pour | R5 Cottage - 6/12*
-Foundation walls | R5 Cottage - 6/16*
Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.
Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:
Construction progress aerial footage | May 2023