Development Update - October 2022

October Milestones

New scopes will be starting in the month of October

  • Chapel Structural Steel - 10/4

  • Chapel Wood Framing - 10/11

  • Elevators B/FG - 10/3

  • Roofing - Coping, Flashing, and Trim – 10/5

  • Perforated Metal Panels - 10/7

  • Structural metal framing - J3/J4, J5/J6 Villas

  • Wood framing - J3/J4, J5/J6 Villas

  • Precast window well install - J3/J4, J5/J6 Villas

  • Foundation excavation - H1/H2 Villas

  • Foundation concrete - H1/H2 Villas

Construction progress aerial footage | September 2022


Trucking Impacts

  • Insulation & Drywall – Approximately 3 trucks per week*

  • Structural Steel – Approximately 2 trucks per week*

  • Brick Veneer – Approximately 2 trucks per week*

  • MEPF Material – Approximately 6 trucks per week*

  • Roofing Material – Approximately 1 truck per week*

  • Wood Framing Material – Approximately 3 trucks per week*

  • Fireplaces / Mantel Material – Approximately 1 truck per week*

  • Shower Doors – Approximately 1 truck per week*

  • Storefront / Glass Partitions – Approximately 1 truck per week*

  • Unit Appliances – Approximately 1 truck per week*

  • Patio Pavers – Approximately 1 truck per week*

  • Balcony Railings – Approximately 2 trucks per week*

  • Flooring Material – Approximately 3 trucks per week*

  • Cabinets / Millwork – Approximately 2 trucks per week*

  • Interior Doors & Trim – Approximately 3 trucks per week*

  • Irrigation/Landscaping Material – Approximately 2 trucks per week*

  • Underground Utility Material – Approximately 2 trucks per week*

  • Concrete Pour Dates

    • Building – K (Pool)

Form and Pour Pool Deck – 10/24 ~15-20 trucks*

  • Building E (Reception)

Footings Sequence 1 | 9/30 ~5 trucks*

Footings Sequence 2 | 10/10 ~5 trucks*

Foundation Walls Pour #1 | 10/11 ~10 trucks*

Foundation Walls Pour #2 | 10/19 ~10 trucks*

Slab on Metal Deck | 11/9 ~15-20 trucks*

  • H1/H2 Villas

Piers | 10/7 - 10/12 ~12-15 trucks total*

Foundation Walls | 10/28 - 10/30 ~15-17 trucks total*



Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.

Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:

Construction progress aerial footage | September 2022


General Construction Activity

Overall site

  • Roofing

  • Parapet Caps / Gutters / Downspouts

  • Brick Veneer / Stone

  • Siding / Trim

  • Structural Steel

  • Wood Framing

  • Cabinets

  • Gypcrete

  • Interior Doors

  • Insulation & Drywall

  • Wood Flooring, Base, Tile

  • Carpet

  • Shower Doors

  • Bathroom Accessories

  • Unit Appliances

  • Countertops

  • Painting (Interior & Exterior)

  • Balcony Railings

  • Patio Pavers

  • Fireplaces

  • Glass Partitions / Storefront

  • Ceiling Grid & Tile

  • Elevator Installation

  • MEPF Rough In & Trim Out

  • Excavation / Backfill

  • Storm / Underground Utilities

  • Site Work

Villas

  • Framing

  • Excavation

  • Backfill

  • Concrete pier drilling/pour

  • Concrete foundation forming/pour

  • Waterproofing/perimeter drain