October Milestones
New scopes will be starting in the month of October
Chapel Structural Steel - 10/4
Chapel Wood Framing - 10/11
Elevators B/FG - 10/3
Roofing - Coping, Flashing, and Trim – 10/5
Perforated Metal Panels - 10/7
Structural metal framing - J3/J4, J5/J6 Villas
Wood framing - J3/J4, J5/J6 Villas
Precast window well install - J3/J4, J5/J6 Villas
Foundation excavation - H1/H2 Villas
Foundation concrete - H1/H2 Villas
Construction progress aerial footage | September 2022
Trucking Impacts
Insulation & Drywall – Approximately 3 trucks per week*
Structural Steel – Approximately 2 trucks per week*
Brick Veneer – Approximately 2 trucks per week*
MEPF Material – Approximately 6 trucks per week*
Roofing Material – Approximately 1 truck per week*
Wood Framing Material – Approximately 3 trucks per week*
Fireplaces / Mantel Material – Approximately 1 truck per week*
Shower Doors – Approximately 1 truck per week*
Storefront / Glass Partitions – Approximately 1 truck per week*
Unit Appliances – Approximately 1 truck per week*
Patio Pavers – Approximately 1 truck per week*
Balcony Railings – Approximately 2 trucks per week*
Flooring Material – Approximately 3 trucks per week*
Cabinets / Millwork – Approximately 2 trucks per week*
Interior Doors & Trim – Approximately 3 trucks per week*
Irrigation/Landscaping Material – Approximately 2 trucks per week*
Underground Utility Material – Approximately 2 trucks per week*
Concrete Pour Dates
Building – K (Pool)
Form and Pour Pool Deck – 10/24 ~15-20 trucks*
Building E (Reception)
Footings Sequence 1 | 9/30 ~5 trucks*
Footings Sequence 2 | 10/10 ~5 trucks*
Foundation Walls Pour #1 | 10/11 ~10 trucks*
Foundation Walls Pour #2 | 10/19 ~10 trucks*
Slab on Metal Deck | 11/9 ~15-20 trucks*
H1/H2 Villas
Piers | 10/7 - 10/12 ~12-15 trucks total*
Foundation Walls | 10/28 - 10/30 ~15-17 trucks total*
Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.
Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:
Construction progress aerial footage | September 2022
General Construction Activity
Overall site
Roofing
Parapet Caps / Gutters / Downspouts
Brick Veneer / Stone
Siding / Trim
Structural Steel
Wood Framing
Cabinets
Gypcrete
Interior Doors
Insulation & Drywall
Wood Flooring, Base, Tile
Carpet
Shower Doors
Bathroom Accessories
Unit Appliances
Countertops
Painting (Interior & Exterior)
Balcony Railings
Patio Pavers
Fireplaces
Glass Partitions / Storefront
Ceiling Grid & Tile
Elevator Installation
MEPF Rough In & Trim Out
Excavation / Backfill
Storm / Underground Utilities
Site Work
Villas
Framing
Excavation
Backfill
Concrete pier drilling/pour
Concrete foundation forming/pour
Waterproofing/perimeter drain