November Milestones
New scopes will be starting in the month of November
Chapel Wood Framing – 11/1
Elevators B/FG – 11/17
Pool Excavation – 11/14
Perforated Metal Panels – 11/14
Foundation concrete - H1/H2 Villas
Backfill - J3/J4/J5/J6 Villas
Retaining Walls - Villas
Utilities - J5/J6 Villas
Waterproofing - H1/H2 Villas
Construction progress aerial footage | October 2022
Trucking Impacts
Insulation & Drywall – Approximately 3 trucks per week*
Cabinets / Millwork – Approximately 2 trucks per week*
Flooring Material – Approximately 3 trucks per week*
Interior Doors & Trim – Approximately 3 trucks per week*
MEPF Material – Approximately 6 trucks per week*
Brick Veneer / Precast – Approximately 1 trucks per week*
Roofing Material – Approximately 2 truck per week*
Shower Doors – Approximately 1 truck per week*
Storefront / Glass Partitions – Approximately 1 truck per week*
Unit Appliances – Approximately 1 truck per week*
Balcony Railings – Approximately 2 truck per week*
Wood Framing Material – Approximately 2 trucks per week*
Irrigation/Landscaping Material – Approximately 2 trucks per week*
Underground Utility Material – Approximately 2 trucks per week*
Concrete Pour Dates
Building – K (Pool)
12/8 Pool Deck - Approximately 15 trucks*
12/19 Walls and Floor - Approximately 15 trucks*
12/20 Pour 1, Slab on Grade Level 1 - Approximately 15 trucks*
Building – E (Reception)
11/7 Footings, Sequence 2 - Approximately 5 trucks*
11/11 Foundation Walls, Sequence 2 - Approximately 10 trucks*
Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.
Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:
Construction progress aerial footage | October 2022
General Construction Activity
Overall site
Insulation & Drywall
Painting (Interior & Exterior)
Wood Flooring, Base, Tile
Cabinets
Doors / Trim
Countertops
Carpet
Ceiling Grid / Wood Ceilings
Roofing
Parapet Caps / Gutters / Downspouts
Brick Veneer / Stone
Siding
Elevators
Structural Steel
Wood Framing
Cabinets
Gypcrete
Shower Doors
Bathroom Accessories
Unit Appliances
Balcony Railings
Patio Pavers
Perforated Metal Panels
Glass Partitions / Storefront
MEPF Rough In & Trim Out
Skylights
Excavation / Backfill
Storm / Underground Utilities
Site Work
Villas
Framing
Excavation
Backfill
Concrete foundation forming/pour
Waterproofing/perimeter drain
Retaining walls
Utility install