July Milestones
New scopes will be starting in the month of July:
Balcony Railings – 7/12
Storefront & Glass Partitions – 7/4
Carpet – 7/12
Unit Appliances – 7/19
Landscaping / Irrigation – 7/19
Site Retaining Walls – 7/5
Trucking Impacts
Unit Appliances – Approximately 1 truck per week*
Patio Pavers – Approximately 1 truck per week*
Balcony Railings – Approximately 1 truck per week*
Flooring Material – Approximately 2 trucks per week*
Cabinets / Millwork – Approximately 1 truck per week*
Interior Doors & Trim – Approximately 2 trucks per week*
Insulation & Drywall – Approximately 3 trucks per week*
Brick Veneer – Approximately 6 trucks per week*
Steel – Approximately 1 trucks per week*
Framing Material – Approximately 1 trucks per week*
MEPF Material – Approximately 5 trucks per week*
Site Retaining Wall Material – Approximately 3 trucks per week*
Irrigation/Landscaping Material – Approximately 1 truck per week*
Underground Utility Material – Approximately 1 truck per week*
Concrete Pour Dates
Chapel Building | Drilled Piers 7/26*
Building – K (Pool)| Walls & Floor 8/9*
Building – E (Breezeway)| Footings 8/5*
Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.
Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:
General Construction Activity
Wood Framing
Structural Steel
Roofing
Brick Veneer
Siding / Trim
Door / Window Installation
Insulation & Drywall
Wood Flooring & Tile
Bathroom Accessories
Unit Appliances
Countertops
Painting (Interior & Exterior)
Balcony Railings
Patio Pavers
Fireplaces
Glass Partitions / Storefront
Ceiling Tile
Elevator Installation
MEPF Rough In
Excavation / Backfill
Storm / Underground Utilities
Site Work