January Milestones
New scopes will be starting in the month of January:
Excavation & Utilities at Building D – 1/4
Elevators B/FG – 1/3
Precast – 1/3
Exterior Metal Panels – 1/11
Elevator Storefronts – 1/9
Pool Building Glass Roof - 1/10
Heavy Timber Roof Structure at Chapel Building – 1/23
Foundation Walls - H1/H2 Villas
Retaining Walls - Villas
Utilities - J5/J6 Villas
Rough MEPs - Villas
Roof Dry-In/Install - Villas
Window Install - Villas
Foundation Waterproofing/Perimeter Drains - Villas
Construction progress aerial footage | December 2022
Trucking Impacts
Insulation & Drywall – Approximately 3 trucks per week*
Cabinets / Millwork – Approximately 4 trucks per week*
Flooring Material – Approximately 2 trucks per week*
Interior Doors & Trim – Approximately 3 trucks per week*
MEPF Material – Approximately 6 trucks per week*
Countertop Material – Approximately 1 truck per week*
Brick Veneer / Precast – Approximately 3 trucks per week*
Roofing Material – Approximately 1 truck per week*
Storefront / Glass Partitions – Approximately 1 truck per week*
Unit Appliances – Approximately 1 truck per week*
Balcony Railings – Approximately 2 truck per week*
Wood Framing Material – Approximately 3 trucks per week*
Irrigation/Landscaping Material – Approximately 3 trucks per week*
Underground Utility Material – Approximately 3 trucks per week*
Lumber delivery | Villas – approximately 2 trucks per week*
Rebar delivery | Villas – approximately 2 trucks*
Steel delivery | Villas – approximately 4-6 trucks*
Concrete Pour Dates*
Building – K (Pool)
- Walls and Floor – 1/26 - approximately 15 trucks*
- Pour 1, Slab on Grade Level 1 – 2/3 - approximately 15 trucks*
Building – B (Trellis)
- Slab on Grade Level 1 – 1/7 - approximately 2 trucks*
H1/H2 Villas
- Foundation walls – 1/11 - approximately 15-17 trucks*
Road Closures
4th Street Work – 1/1/23
Public access will be closed beginning 1/1/23 and will re-open/close throughout the month. Access will be available to residences within the closed area throughout the duration of work.
- South of Maxwell to alley – closed 1/3 – 1/6 & 1/9 – 1/23
- North of Maxwell to alley – 1/1 – 1/16 & 1/18 – 1/23
4TH STREET WORK/ROAD CLOSURE UPDATE 1/13/23
New dates: Monday 1/16/23 through Wednesday 1/18/23. There is a small possibility of clean up work on Thursday.
The entrance to the jobsite will be shut down as will 4th Street on both sides of Maxwell. Revised traffic control plan below.
Water Shut Down: Tuesday 1/17/23, 8:00 am - 4:00 pm. Any building along 4th street between Maxwell and Mapleton will be without water during this time. All affected properties will receive notification from the public utility provider/contractor. The contractor will make every effort to turn water supply back on before the estimated restoration time of 4pm.