top of page
Writer's picture311 Mapleton Development

Development Update - February 2023

February Milestones

New scopes will be starting in the month of February:

  • Precast – 2/16

  • Exterior Metal Panels – 2/14

  • Elevator Storefronts – 2/13

  • Expansion Joints – 2/14

  • Pool Exterior Skin (Siding / Stone) – 2/2

  • Pool Building Glass Roof - 1/10

  • Heavy Timber Roof Structure at Chapel Building – 2/6

  • Elevators at Building B – 2/1

  • Brick Veneer/Precast at Building B – 2/6

  • Foundation Walls - J1/J2 Villas

  • Retaining Walls

  • Utilities - J5/J6 Villas

  • Rough MEPs

  • Roof Dry-In/Install

  • Window Install

  • Foundation Waterproofing/Perimeter Drains

  • Xcel gas/electrical lines

Construction progress aerial footage | January 2023


Road Closures


Public access will be affected February/beginning of March. *Please note the entire road will not be closed, only one side, leaving access for vehicles to pass with help from a flagger. That portion of road will be closed the night before to prevent people from parking there early in the morning.


Road Impact #1 -Tree removal and waterline installation

  • 2/8 - 2/17: Three trees will be removed, and a new waterline will be installed

Road Impact #2 and #3 - Partial 4th Street Closure

  • 2/27 - 2/28: Fire Hydrant Installation

  • 3/2 - 3/6: Concrete replacement

  • 3/7 - 3/8: Asphalt replacement

Road Impact #4 - Partial 4th Street Closure

  • 3/1: Fire Hydrant Installation

  • 3/2 - 3/6: Concrete replacement

  • 3/7 - 3/8: Asphalt replacement

Road Impact #5 - Partial 4th Street Closure

  • 3/6: Abandonment of existing waterline - Work performed by The City of Boulder*

  • 3/6 - 3/8: Concrete replacement

  • 3/7 - 3/8: Asphalt replacement


Trucking Impacts

  • Insulation & Drywall – Approximately 4 trucks per week*

  • Cabinets / Millwork – Approximately 4 trucks per week*

  • Flooring Material – Approximately 2 trucks per week*

  • Interior Doors & Trim – Approximately 3 trucks per week*

  • Hollow Metal Doors – Approximately 2 trucks per week *

  • MEPF Material – Approximately 6 trucks per week*

  • Countertop Material – Approximately 2 truck per week*

  • Brick Veneer / Precast – Approximately 1 trucks per week*

  • Roofing Material – Approximately 1 truck per week*

  • Storefront / Glass Partitions – Approximately 3 truck per week*

  • Unit Appliances – Approximately 3 truck per week*

  • Balcony Railings – Approximately 3 truck per week*

  • Siding Material – Approximately 1 truck per week *

  • Wood Framing Material – Approximately 2 trucks per week*

  • Irrigation/Landscaping Material – Approximately 3 trucks per week*

  • Underground Utility Material – Approximately 3 trucks per week*

  • Lumber delivery – Villas - Approximately 2 trucks per week*

  • Rebar delivery – Villas - Approximately 3 trucks

  • Steel delivery – Villas - Approximately 2-3 trucks

  • Concrete Pour Dates

    • Building – K (Pool)

- Walls and Floor – 2/23 - approximately 15 trucks*

- Pour 1, Slab on Grade Level 1 – 3/3 - approximately 15 trucks*

  • Building – E (Reception)

- Slab on Metal Deck – 3/1 (approximately 10 trucks)*

- Concrete Sidewalks & Stairs – 2/16 (approximately 2 trucks)

  • Building – A (Site Work)

- Concrete Sidewalks & Stairs – 3/2 - approximately 3 trucks

- Slab on Grade for Pavers at Courtyard – 3/2 - approximately 2 trucks

  • Building – B (Site work)

- Pour Bridge Deck and Stairs – 3/3 - approximately 2 trucks

  • H1/H2 Villas

- Foundation walls – 2/2 approximately 15-17 trucks*

  • J1/J2 Villas

- Foundation Piers – 2/23 – 2/28 - approximately 10 trucks*


Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.


Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:

bottom of page