February Milestones
New scopes starting in February:
Interior Finishes – 2/15
The new communication forum will debut this Friday, 2/11/22. Access information will be posted on our website and sent to our subscriber list once the system is live, so keep an eye out for that!
Construction progress aerial footage | January 2022
Trucking Impacts
Roofing Material | Approximately 4 trucks per week*
Insulation & Drywall | Approximately 3 trucks per week*
Brick Veneer | Approximately 6 trucks per week*
Steel | Approximately 1 trucks per week*
MEPF Rough-in Material | Approximately 4 trucks per week*
Doors & Windows – Approximately 1 truck per week*
Concrete Pour Dates | Approximately 2-10 trucks per day outside of dates noted below:
Large slab pour dates that will range from 40 to 80 delivery trucks:
2/12/22 – A-West Level 1 Slab on Grade*
2/25/22 – A-West Suspended Slab Pour*
Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.
Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:
In Progress Milestones from Previous Month(s)
Roofing - 11/10/21
Brick Veneer – 1/3/22
Skylights – 1/10/22
Elevator Installation – 1/7/22
Insulation & Drywall – 1/24/22
Fireplace Installation – 1/5/22
Construction progress aerial footage | January 2022