April Milestones
New scopes will be starting in the month of April:
Exterior Metal Panels – 4/6
Garage Doors – 4/13
Pool Building Glass Roof – 4/6
Site Pavers – 4/14
Heavy Timber Roof Structure at Chapel Building – 4/5
Building E (Reception) Roofing – 4/7
Site Concrete: A-Courtyard, A-South (All Month)
Site Ponds (All Month)
Foundations - J1/J2 Villas
Foundation Walls - J1/J2 Villas
Framing - H1/H2 + J1/J2 Villas
Utilities - H1/H2 Villas
Rough MEPs - Villas
Window Install - Villas
Siding Install - Villas
Fireplace Install - Villas
Window Well Install - Villas
Fire Suppression - Villas
Insulation - Villas
Stake out new foundation - R5/R6/R7 Cottages
Removal of existing non-operable utilities - R5/R6/R7 Cottages
Construction fence install - R5/R6/R7 Cottages
Excavation - R6/R7 Cottages
Footing install - R6/R7 Cottages
Foundation walls - R6/R7 Cottages
Construction progress aerial footage | March 2023
Trucking Impacts
Insulation & Drywall – Approximately 3 trucks per week*
Site Paver Material – Approximately 1 truck per week*
Rosch Retaining Wall Material – Approximately 2 trucks per week*
Structural Steel – Approximately 1 truck per week *
Pool Tile & Finishes – Approximately 1 truck per week*
Cabinets / Millwork – Approximately 4 trucks per week*
Flooring Material – Approximately 2 trucks per week*
Interior Doors & Trim – Approximately 3 trucks per week *
MEPF Material – Approximately 6 trucks per week*
Countertop Material – Approximately 3 truck per week*
Brick Veneer / Precast – Approximately 2 trucks per week*
Roofing Material – Approximately 1 truck per week*
Storefront / Glass Partitions – Approximately 2 truck per week*
Unit Appliances – Approximately 3 trucks per week*
Balcony Railings – Approximately 3 trucks per week*
Siding Material – Approximately 1 truck per week*
Wood Framing Material – Approximately 2 trucks per week*
Irrigation/Landscaping Material – Approximately 3 trucks per week*
Underground Utility Material – Approximately 3 trucks per week*
Patio Precast Material – Approximately 1 truck per week
Hauling off excess site dirt - Approximately 4 trucks per week
Lumber delivery | Villas – approximately 2 trucks per week*
Rebar delivery | Villas – approximately 3 trucks*
Steel delivery | Villas – approximately 2-3 trucks*
Concrete delivery | Villas - approximately 12 trucks*
Material delivery - R5/R6/R7 Cottages - approximately 3 trucks/day April 3-7th*
Material delivery - R5/R6/R7 Cottages - approximately 3 trucks/day April 10th-12th*
Concrete Pour Dates
Building – K (Pool)
- Pool Deck – 4/17 - approximately 1 truck*
Site
- Approximately 9 trucks per week - all month*
J1/J2 Villas
- Foundation Walls - 4/7 - approximately 12 trucks*
R6/R7 Cottages
- Footings | R6 and R7 - 4/12 - 4/20 - 5 trucks total*
- Foundation Walls | R7 - 4/17 – 4/21 - 10 trucks total*
- Foundation Walls | R6 - 4/24 – 4/28 - 10 trucks total*
4th Street Work / Public Access
Public access may be affected through the month of April. Traffic Control Plan will be in place.
4th Street Work
- Fire Hydrant Installation – Entire month of April
Mapleton Avenue
- Fire Hydrant Installation
Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.
Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles:
Construction progress aerial footage | March 2023
Comments