April Milestones
New scopes starting in the month of April:
Wood and Tile Flooring – 4/19/22
Millwork & Cabinets– 4/26/22
Interior Doors & Trim – 4/26/22
Painting – 4/12/22
Pool Foundation/SOG – 4/1/22
Construction progress aerial footage | March 2022
In Progress Milestones from Previous Months
Brick Veneer – 1/3/22
Elevator Installation – 1/7/22
Insulation & Drywall – 1/24/22
Fireplace Installation – 1/5/22
Interior Finishes – 2/15/22
Storm/Underground Utilities – 3/23/22
Ceiling Grid – 3/7/22
Trucking Impacts
Flooring Material | Approximately 2 trucks per week*
Cabinets / Millwork | Approximately 1 truck per week*
Interior Doors & Trim | Approximately 2 trucks per week*
Roofing Material | Approximately 2 trucks per week*
Insulation & Drywall | Approximately 3 trucks per week*
Brick Veneer | Approximately 6 trucks per week*
Steel | Approximately 2 trucks per week*
Framing Material | Approximately 3 trucks per week*
MEPF Material | Approximately 4 trucks per week*
Concrete Pour Dates | Approximately 2-10 trucks per day outside of dates noted below:
Large slab pour dates that will range from 40 to 80 delivery trucks:
Monday 5/2/22 | Building K (Pool) slab on grade pour
Construction progress aerial footage | January - March 2022