top of page
Writer's picture311 Mapleton Development

Development Update - April 2022

April Milestones

New scopes starting in the month of April:

  • Wood and Tile Flooring – 4/19/22

  • Millwork & Cabinets– 4/26/22

  • Interior Doors & Trim – 4/26/22

  • Painting – 4/12/22

  • Pool Foundation/SOG – 4/1/22

Construction progress aerial footage | March 2022


In Progress Milestones from Previous Months

  • Brick Veneer – 1/3/22

  • Elevator Installation – 1/7/22

  • Insulation & Drywall – 1/24/22

  • Fireplace Installation – 1/5/22

  • Interior Finishes – 2/15/22

  • Storm/Underground Utilities – 3/23/22

  • Ceiling Grid – 3/7/22

Trucking Impacts

  • Flooring Material | Approximately 2 trucks per week*

  • Cabinets / Millwork | Approximately 1 truck per week*

  • Interior Doors & Trim | Approximately 2 trucks per week*

  • Roofing Material | Approximately 2 trucks per week*

  • Insulation & Drywall | Approximately 3 trucks per week*

  • Brick Veneer | Approximately 6 trucks per week*

  • Steel | Approximately 2 trucks per week*

  • Framing Material | Approximately 3 trucks per week*

  • MEPF Material | Approximately 4 trucks per week*

  • Concrete Pour Dates | Approximately 2-10 trucks per day outside of dates noted below:

Large slab pour dates that will range from 40 to 80 delivery trucks:

  • Monday 5/2/22 | Building K (Pool) slab on grade pour


Construction progress aerial footage | January - March 2022



bottom of page