• 311 Mapleton Development

Development Update 5/15/20

Hauling Activities


The previous development update published on May 8, 2020 indicated that overlot grading and excavation on site would continue while utilities are being installed, but that hauling would be paused for the duration of utility work. However, after a week of no hauling and an accumulation of dirt and other materials, it has become apparent that some hauling will need to continue. As such, the team will resume hauling activities effective Saturday May 16, and will continue to haul materials off-site most Saturdays. Hauling will remain paused from Sunday through Friday while utility work takes place.  A portion of the dirt that has accumulated up to this point will be relocated to other areas on site to be used as infill in the coming weeks as well. 

Recent Posts

See All

10/23/20 Hauling + Development Update

The estimated completion date for current hauling and excavation is now the first week of November. This extension is due to eight days of no hauling from 9/28 - 10/7, continued difficulties with dens

Paving Operation Rescheduled for Monday 9/21

The paving operation initially scheduled for tomorrow, Saturday 9/19, will now occur on Monday, 9/21. The road prep crew has not made enough progress and needs another day for compaction and grading b

Never miss an update | Join our mailing list

Contact Us

info@311mapleton.com

720.507.7537

or submit an inquiry on our contact page.

©2018 by 311 Group LLC | Proudly created with Wix.com