• 311 Mapleton Development

Development Update 4/14/20

The critical path for development of 311 Mapleton prior to the completion of demolition was originally slated for the installation of underground utilities. However, due to the closure of City offices per the stay-at-home order, the necessary inspections and permits are unable to be obtained for utility work. In the interim, the critical path has shifted to overlot grading and excavation.


There will be days that the dirt is stockpiled on site for future use, and others where it will be trucked off site. There will be 5 trucks running approximately 6-8 trips per truck/day when hauling is active.


All trucks will follow the routes laid out in our Construction Management and Good Neighbor Plan as shown below. 



25 views0 comments

Recent Posts

See All

12/8/20 Development Update

Hauling will occur Thursday 12/10 and Friday 12/11 to remove the last bit of unsuitable material from over-excavation. The team anticipates 4-5 trucks day round-tripping dirt/rock off-site on Thursday

11/9/20 Hauling + Development Update

Hauling for the current excavation phase officially concluded Thursday, 11/05/20. As stated in the Construction Management and Good Neighbor Plan: hauling will be active for the duration of infrastruc

11/2/20 Hauling + Development Update

Last week's snowstorm caused a pause in hauling from 10/26 - 10/31 due to significant ground saturation. Hauling will recommence Monday, 11/2, following this weather delay. Continuation of excavation