• 311 Mapleton Development

Development Update 4/14/20

The critical path for development of 311 Mapleton prior to the completion of demolition was originally slated for the installation of underground utilities. However, due to the closure of City offices per the stay-at-home order, the necessary inspections and permits are unable to be obtained for utility work. In the interim, the critical path has shifted to overlot grading and excavation.


There will be days that the dirt is stockpiled on site for future use, and others where it will be trucked off site. There will be 5 trucks running approximately 6-8 trips per truck/day when hauling is active.


All trucks will follow the routes laid out in our Construction Management and Good Neighbor Plan as shown below. 



Recent Posts

See All

10/23/20 Hauling + Development Update

The estimated completion date for current hauling and excavation is now the first week of November. This extension is due to eight days of no hauling from 9/28 - 10/7, continued difficulties with dens

Paving Operation Rescheduled for Monday 9/21

The paving operation initially scheduled for tomorrow, Saturday 9/19, will now occur on Monday, 9/21. The road prep crew has not made enough progress and needs another day for compaction and grading b