Demolition Progress Update

The demolition phase is coming to an end on the 311 Mapleton site!


  • The main hospital building is mostly demolished, and the majority of materials have been shipped off site as of 1/27, except for the pool

  • The pool is estimated to be completed by the beginning of February 

  • No accidents on site to date

  • There are two dedicated team members assigned to collecting any loose or wind-blown debris on site and surrounding the property

  • There are currently 5 trucks hauling materials, doing 4 trips per day for a total of 20 trips per day estimated through the end of demolition.



Once the pool has been demolished, the crew will continue to work on small punch-list items, and anticipate demolition to be completed by the end of February 2020.

Recent Posts

See All

Paving Operation Rescheduled for Monday 9/21

The paving operation initially scheduled for tomorrow, Saturday 9/19, will now occur on Monday, 9/21. The road prep crew has not made enough progress and needs another day for compaction and grading b

Never miss an update | Join our mailing list

Contact Us

info@311mapleton.com

720.507.7537

or submit an inquiry on our contact page.

©2018 by 311 Group LLC | Proudly created with Wix.com