• 311 Mapleton Development

9/21 - 9/27 Development Activity Information

Here's what to expect for the week of 9/21 - 9/27: 

  • Paving operation on Monday, 9/21 - full details listed here

  • Continuation of excavation with 8-10 trucks round-tripping dirt off-site each day. Hauling will not be active while paving is underway.

  • Installation of storm line on the NE corner of the property, as shown in the picture below.


24 views0 comments

Recent Posts

See All

12/8/20 Development Update

Hauling will occur Thursday 12/10 and Friday 12/11 to remove the last bit of unsuitable material from over-excavation. The team anticipates 4-5 trucks day round-tripping dirt/rock off-site on Thursday

11/9/20 Hauling + Development Update

Hauling for the current excavation phase officially concluded Thursday, 11/05/20. As stated in the Construction Management and Good Neighbor Plan: hauling will be active for the duration of infrastruc

11/2/20 Hauling + Development Update

Last week's snowstorm caused a pause in hauling from 10/26 - 10/31 due to significant ground saturation. Hauling will recommence Monday, 11/2, following this weather delay. Continuation of excavation