• 311 Mapleton Development

6/4 - 6/5 Truck Routing Adjustment

Due to an emergency shut down by Xcel Energy on Alpine Ave, hauling will be routed to Dellwood Ave today. Alpine Ave will be used tomorrow, June 5th, to disperse the impact. Hauling will return to normal operations Monday, June 8th. We apologize for the inconvenience and appreciate your patience.


Hauling is currently active Monday through Friday, as unforeseen conditions were discovered in 4th Street, thus halting utility work. Hauling will not be active on Saturday in the interim, and an update will be provided once utility work has been scheduled to resume. 

32 views0 comments

Recent Posts

See All

12/8/20 Development Update

Hauling will occur Thursday 12/10 and Friday 12/11 to remove the last bit of unsuitable material from over-excavation. The team anticipates 4-5 trucks day round-tripping dirt/rock off-site on Thursday

11/9/20 Hauling + Development Update

Hauling for the current excavation phase officially concluded Thursday, 11/05/20. As stated in the Construction Management and Good Neighbor Plan: hauling will be active for the duration of infrastruc

Never miss an update | Join our mailing list

Contact Us

info@311mapleton.com

720.507.7537

or submit an inquiry on our contact page.

©2018 by 311 Group LLC | Proudly created with Wix.com