Hauling will occur Thursday 12/10 and Friday 12/11 to remove the last bit of unsuitable material from over-excavation.


The team anticipates 4-5 trucks day round-tripping dirt/rock off-site on Thursday and will push to finish that day. Depending on Thursday's progress, there may be 1-2 trucks round-tripping on Friday to complete removal.

7 views0 comments

Recent Posts

See All

11/9/20 Hauling + Development Update

Hauling for the current excavation phase officially concluded Thursday, 11/05/20. As stated in the Construction Management and Good Neighbor Plan: hauling will be active for the duration of infrastruc

11/2/20 Hauling + Development Update

Last week's snowstorm caused a pause in hauling from 10/26 - 10/31 due to significant ground saturation. Hauling will recommence Monday, 11/2, following this weather delay. Continuation of excavation

10/23/20 Hauling + Development Update

The estimated completion date for current hauling and excavation is now the first week of November. This extension is due to eight days of no hauling from 9/28 - 10/7, continued difficulties with dens