General Requirements
• Work hours – All local codes and governing jurisdiction requirements will be strictly enforced, pursuant to The Boulder Municipal Code Section 5-9-3, B.R.C, 1981.
• Badging of each employee once site orientation has been completed.
• Secure site perimeter at all times and locked gates after hours.
• All COVID-19 health guidelines produced by the CDC and CDPHE will be adhered to until further notice.
Code of Conduct
• Being under the influence of or in possession of alcohol or drugs is not permitted. The worksite will be an alcohol and drug free zone.
• No smoking will be allowed in the public right of way. Designated smoking areas will be assigned on-site.
• Imminent Danger and safety violations will result in removal from the project.
• Loud or obnoxious noises (swearing, yelling, whistling, etc..) or behavior that appears harassing or obscene (staring, gesturing, etc..) will not be tolerated. Everyone will behave in a professional manner on the site.
• Audio equipment (radios, TV’s, CD’s, MP3, iPods, etc..) are not allowed.
• Offensive clothing is not allowed. Clothing must not display obscene pictures, graphics, messages, or double meaning statements.
• Taking breaks of any duration outside of the confines of the construction site will not be allowed.
Minimum Required PPE (Personal Protective Equipment)
• Safety Glasses
• Hard Hat
• Work Boots
• T-shirt and Long Pants
• Facemasks, until further notice by CDC, OSHA and CDPHE
Housekeeping
• Work areas will be kept free of accumulated scrap materials. Trash, scraps, cribbing, pallets, packaging, etc. will be placed in job-site trash containers in an effort to keep trash from being windblown.
• Material sorting and recycling will be an on-going effort by the contractor throughout the project
• Efforts will be made daily to ensure no trash accumulates on public right of ways outside the project boundaries.
• Contractor will perform periodic walks of adjacent areas to the site and clean up any potential debris that has been blown from the site.
Fire Prevention
• All infrastructure and fire protection measures will be in place prior to start of combustible construction.
• The Fire Department has been given gate access codes and keys for all buildings on the site in case of an emergency.
• Portable fire extinguishers will be located for every 3,000 sq. feet of work area.
• Portable fire extinguishers will be located in the immediate vicinity of hot work. Hot work is to include all spark or flame producing activities. This includes grinding and welding.
• Flammables will be stored in approved containers, quantities, and locations with appropriate fire protection meeting regulatory requirements.
Equipment Operation
• Employees operating equipment on this jobsite must be trained and authorized. This includes, but is not limited to skid steers, water trucks, forklifts, trenchers, aerial lifts, etc.
Stormwater Requirements
• The contractor will have stormwater protections established and maintained for the duration of the project In accordance with City of Boulder and State of Colorado Standards.
• Boulder Inspectors as well as third party Inspectors will regularly verify compliance.